Progress Meeting #12
03-03-09
Current Work Activities:
1. Gym Floor Poured Tomorrow
(7-10 days cure time)
2. Prep for brick begins today
3. Music Room – move in target date – Friday, April 3rd
3. Start roof insulation
4. Continue metal framing
5. Continue roof blocking
6. Cabinets in the Music Room delivered and installed March 23.
|