Construction Meeting
Tuesday, November 18, 2008
CURRENT WORK ACTIVITIES:
- Foundation blocks
- Begin masonry
TWO WEEK LOOK AHEAD:
- The music room will need to re-locate by the end of day,
Tuesday, November 25, 2008
- Target date for occupancy back to the music room (end of Phase I) is
April 23, 2009
- A 8x8x20 foot POD will be delivered to store furniture and supplies from
the music room and the stage during the building project
SAFETY CONCERNS:
- A temporary light will be hooked up in the parking lot ASAP
Next meeting: December , 2008, 10:30 A.M., Construction Trailer |